- Repeat Client
- Additions and renovations to Niles North and Niles West high schools
- 250,000 sq. ft. of additions
- 200,000 sq. ft. of renovations
- Phased over 2-1/2 years so that there is no interruption to the educational process
- All new mechanical system for both schools
- All renovation work completed over summer recess
- 2006: Four-classroom science lab conversion
June 2001 through December 2003 $110 million Construction Management contract
Niles Township High School District 219 Skokie, IL
Legat Architects Crystal Lake, IL
|